(1)

Except in the case of an external leader, after a section of drainage system or a venting system has been roughed in, and before any fixture is installed or piping is covered, a water or an air test shall be conducted.

(2)

After every fixture is installed and before any part of the drainage system or venting system is placed in operation, a final test shall be carried out when requested by the chief building official.

(3)

Where a prefabricated system is assembled off the building site in such a manner that it cannot be inspected and tested on site, off-site inspections and tests shall be conducted.

(4)

Where a prefabricated system is installed as part of a drainage system or venting system, all other plumbing work shall be tested and inspected and a final test shall be carried out on the complete system when requested.

(5)

A ball test shall be carried out on a sanitary building drain, sanitary building sewer, storm building drain and a storm building sewer buried underground.

(6)

A sewer lateral extension need not be tested and inspected if the sewer lateral extension was constructed, tested and inspected at the time of the installation of the public sewer.